Major Steps |
Steps |
|
| Physical System Design |
Physical Design |
- Physical Data Design
- Process Data Interface
- Data Catalogue
- Program Specification
- Performance Optimization Report (= SSADM Stage 6 deliverables)
|
| Program Development |
Program coding |
- Software modules
- Job control procedures
- Unit Test cases
- Program Documentation
|
| Unit Testing |
|
| System Integration & Testings |
Link / Function / Systems Testing |
- Various levels of Test plan, Test specification & Test results
|
| User Acceptance Rehearsal |
- Software modules in integration
|
| User Acceptance Testing & Training |
User Acceptance Testing |
- User Acceptance Test plan, Test specification & Test results
|
| User training |
- "Passing tests" software modules
- Training on both computer system and computer concepts
|
| System Installation & Production |
Site Preparation |
- Site specification
- Accepted site
|
| Documentation |
- Application User Manual
- Application Operation Manual
- Computer Operating Procedures Manual
- System Manual
- Program Manual
- Data Manual
|
| System Installation |
- System Installation Plan
- Hardware and software modules in integration
- System Installation Report
|
| Conversion |
- Conversion Plan (old data converted into new system)
- Conversion Report
|
| System Production |
- Computer Systems in production use
|
| Project Evaluation Review |
Project Evaluation Review |
- Project Evaluation Report
|
Major Steps |
Steps |
|
| Physical System Design, Program Development, System Integration &Testing, User Acceptance Testing |
Rapid Construction |
- Database/File Specification
- Program Specifications
- Various Level of Test Plan
- Test Cases, Test Data and Test Results
- Training Plan and Material
- Programs
- Data Conversion Routine (if any)
|
| User Training, System Installation & Production |
Transition |
- Computing Environment
- Application User Manual
- Application Operation Manual
- Computer Operation Procedures Manual
- System Manual
- Program Manual
- Data Manual
- Converted Data (if any)
- Trained User
|
| Project Evaluation Review |
|
- Project Evaluation Report
|